As a subcontractor, our work sits inside our customers’ contracts with their clients. Each example states the programme, who our customer is, what we do on it and where it stands now.

Fibre network civils for SIRO and National Broadband Ireland

Fibre civils across Dublin and the neighbouring counties, carried out street by street from the main contractors’ work instructions. Much of the work put new sub-duct into existing ESB and eir ducts, with blockage clearance, new duct and chambers where the route needed them, and reinstatement behind every opening. It included duct routes for data-centre connections and work inside business parks.

Networks
SIRO fibre-to-the-building and National Broadband Ireland
Area
Dublin, Meath and Wicklow
Our customers
Entegro and Gaeltec Utilities
Our role
Civils subcontractor
Status
Works delivered 2024 to 2026

Our scope

  • Rodding and roping existing ducts, and installing distribution and feeder sub-ducts
  • Duct blockage location and clearance
  • Silt and debris clearance from chambers
  • Trial holes to locate existing services
  • New duct by open trench, chambers and road crossings
  • Duct routes for data-centre connections
  • Temporary and permanent reinstatement of footpaths, verges, block paving and carriageway

Site constraints

  • Housing estates, town centres, business parks and secure sites
  • Existing ducts shared with live cables
  • Network operator rules, inductions and audits
  • Road-opening licences and traffic management

Records

  • Completion records for the network operator’s mapping
  • Photographs to the operator’s audit standard

Public lighting civils across Dublin City

Civils for the replacement of public lighting columns, delivered street by street under road-opening licences: breakout, ducting, chambers, column removal and installation, and reinstatement of the footpath and road.

A long open trench in a concrete footway with red duct laid along the bottom, a coil of duct beside it and a mini excavator behind.
Duct laid in an open footway trench
A CAT mini excavator digging a duct trench along a footway, with pedestrian barriers along the road edge.
Trenching behind pedestrian barriers
A red duct running from a mini-pillar through an open excavation, with cable warning tape at the edge.
Duct run to a mini-pillar
A long run of new concrete footway beside a road on a sunny day.
Finished concrete footway
Programme
Dublin City Council public lighting upgrade
Area
Dublin City
Our customers
Al Read Electrical and KLM Utilities
Our role
Civils subcontractor
Status
In progress

Our scope

  • Route walks with the road authority and the main contractor
  • Breakout and excavation at column positions
  • Trenching and ducting between columns and to feeder pillars, including road crossings
  • Junction-box chambers
  • Column removal and installation
  • Reinstatement of concrete footpaths, kerbs, tactile paving, block paving and driveways

Site constraints

  • Occupied residential streets with parked cars and pedestrians
  • Working hours and conditions set by road-opening licences
  • Openings made safe before each working window closes
  • Live cables and other buried services

Records

  • Photographs and measurements for every column and duct run
  • Defects recorded and closed out

Concrete reinstatement after water-network works

Concrete reinstatement of excavations made on water-network works across Dublin, issued site by site.

Works
Water-network excavations
Area
Dublin
Our customer
GMC Utilities
Our role
Reinstatement subcontractor
Status
Ongoing

Our scope

  • Concrete reinstatement of excavations
  • Measurement of each reinstatement

Records

  • Measurements and photographs for each site

Contact