Skip to content

Project example

Public lighting civils across Dublin City

Civils for the replacement of public lighting columns, delivered street by street under road-opening licences: breakout, ducting, chambers, column removal and installation, and reinstatement of the footpath and road.

Project details

Programme
Dublin City Council public lighting upgrade
Area
Dublin City
Our customers
Al Read Electrical and KLM Utilities
Our role
Civils subcontractor
Status
In progress
A long open trench in a concrete footway with red duct laid along the bottom, a coil of duct beside it and a mini excavator behind.
Duct laid in an open footway trench
A CAT mini excavator digging a duct trench along a footway, with pedestrian barriers along the road edge.
Trenching behind pedestrian barriers
A red duct running from a mini-pillar through an open excavation, with cable warning tape at the edge.
Duct run to a mini-pillar
A long run of new concrete footway beside a road on a sunny day.
Finished concrete footway

Our scope

  • Route walks with the road authority and the main contractor
  • Breakout and excavation at column positions
  • Trenching and ducting between columns and to feeder pillars, including road crossings
  • Junction-box chambers
  • Column removal and installation
  • Reinstatement of concrete footpaths, kerbs, tactile paving, block paving and driveways

Site constraints

  • Occupied residential streets with parked cars and pedestrians
  • Working hours and conditions set by road-opening licences
  • Openings made safe before each working window closes
  • Live cables and other buried services

Records at handover

  • Photographs and measurements for every column and duct run
  • Defects recorded and closed out

Services used

Contact

Have a similar project?