Project example
Fibre network civils for SIRO and National Broadband Ireland
Fibre civils across Dublin and the neighbouring counties, carried out street by street from the main contractors’ work instructions. Much of the work put new sub-duct into existing ESB and eir ducts, with blockage clearance, new duct and chambers where the route needed them, and reinstatement behind every opening. It included duct routes for data-centre connections and work inside business parks.
Project details
- Networks
- SIRO fibre-to-the-building and National Broadband Ireland
- Area
- Dublin, Meath and Wicklow
- Our customers
- Entegro and Gaeltec Utilities
- Our role
- Civils subcontractor
- Status
- Works delivered 2024 to 2026
Our scope
- Rodding and roping existing ducts, and installing distribution and feeder sub-ducts
- Duct blockage location and clearance
- Silt and debris clearance from chambers
- Trial holes to locate existing services
- New duct by open trench, chambers and road crossings
- Duct routes for data-centre connections
- Temporary and permanent reinstatement of footpaths, verges, block paving and carriageway
Site constraints
- Housing estates, town centres, business parks and secure sites
- Existing ducts shared with live cables
- Network operator rules, inductions and audits
- Road-opening licences and traffic management
Records at handover
- Completion records for the network operator’s mapping
- Photographs to the operator’s audit standard
Services used
Fibre and telecoms civils
Sub-duct installation in existing ducts, blockage clearance, new duct and chambers, fibre cable installation and reinstatement for fibre networks and data-centre connections.
Scope and handoverCarriageway and footpath reinstatement
Road openings, carriageway crossings, concrete footpaths, kerbs and paving. Each reinstatement is measured by surface type.